Quality
End-to-end quality — material and work inspection requests, joint sign-off, NCRs, CQA Audit, and repeat-defect/vendor-quality analytics on one record.
One continuous quality record across the full inspection-to-analytics lifecycle. MAS raised - Approved, Material arrives — MIR raised — joint inspection against spec — pass or fail. Work starts — pre-WIR, during-WIR, post-WIR with photo, location, timestamp and joint CM-CQA-EHS-survey-MEP sign-off. Clean closure auto-triggers the bill workflow. Failures become NCRs; NCRs roll into CQA scores; pattern recognition surfaces repeat defects across vendor, project, package, employee. Field photos stay linked to drawing locations, not lost in WhatsApp.
- ·Vendor raises pre-WIR ready signal
- ·WIR scheduled date arrives
- ·MAS raised
- ·Method Statement Submittal (MSS)
- ·MIR scheduled against Client-supplied material handover
- ·Site Engineer + CQA joint inspection completes
- ·NCR raised during inspection or audit
- ·NCR closure submitted by vendor
- ·CQA audit scheduled (cadence or surveillance)
- ·Repeat-defect threshold breach detected
- ·Customer-facing defect pattern surfaced from M22 (Snagg) or M24 (Resident Services)
- ·WO scope and schedule from M14 - Tendering
- ·Drawing version from M07 (Drawing)
- ·Spec from M09 (specs) with inspection acceptance criteria
- ·Vendor record from M13 (VMS) (history, NCR pattern, performance)
- ·Material handover record from M17 (Material)
- ·Previous WIRs against the same activity (for repeat-defect detection)
- ·Project segment from project record
- ·Past-project quality outcomes for comparable scope
- ·SOR (Site Observation Report) history
- ·Pre-WIR submission with photo, location, scope
- ·Drawing reference and spec citation
- ·Test reports where applicable (cube strength, slump, etc.)
- ·Vendor declaration of compliance
- ·NCR raised by Site Engineer or CQA
- ·NCR closure evidence (photo, test result, rework proof)
- ·CQA audit reports
- ·Customer complaints from M24
- ·Pre-WIR through joint inspection through closure workflow with hold-points
- ·MIR workflow for in-house supplied and vendor-supplied material handover
- ·Mobile-based inspection capture with photo, location, timestamp, signature
- ·NCR / SOR digital recording with category, severity, root cause
- ·Pattern recognition — repeat issues across vendor, project, package, material
- ·Customer-facing defect correlation back to source trade
- ·Auto-trigger bill workflow on clean WIR closure
- ·Auto-routing of repeat patterns to vendor performance review
- ·MAS/WIR/MIR workflow procedure
- ·quality objective
- ·NCR classification procedure with severity levels
- ·Bill auto-trigger procedure on clean WIR closure
- ·Inspection escalation procedure on repeat failures
- ·Repeat-defect threshold procedure per category
- ·Customer-defect correlation procedure
- ·Clean WIR closure auto-triggers bill workflow in M21 (billing)
- ·NCR open blocks downstream activity until closed
- ·Major NCR requires CQA Head sign-off on closure
- ·Three repeat NCRs of same type on same vendor auto-flags for CPT review
- ·Customer-facing defect correlates back to vendor on closure
- ·WIR record per inspected activity (pre / during / post)
- ·MAS / MIR record per material handover
- ·NCR / SOR register with status, severity, root cause, closure evidence
- ·Inspection log per package per vendor
- ·CQA Audit Report
- ·Repeat-defect pattern reports per vendor and per package
- ·Customer-defect correlation reports
- ·WIR/MIR status updated through lifecycle
- ·NCR status updated through closure (NCR open >30 days triggers billing to HOLD 30% of amount, variable per project)
- ·Vendor performance updated on every NCR event and closure
- ·Quality status updated per project, per package, per vendor
- ·CQA Audit Report
- ·Clean WIR closure auto-triggers bill workflow in M21 (billing)
- ·NCR and repeat-pattern flags trigger Vendor 360 review in M13 (Vendor Management)
- ·Repeat-pattern reports trigger tender exclusion in M14 (Tendering)
- ·Customer-correlated defects feed M22 (Snagg) snag prediction
- ·WIR closure rate feeds schedule velocity in M16 (Scheduling)
- ·Quality failure triggers root-cause workshop scheduling
- ·Quality alert mechanism — broadcast to design, CPT, CM
- Site EngineerRaises WIRs and MIRs against work and material handover
- CMReadiness sign-off, continuous QC, post-WIR approval, rework follow-up
- CQA EngineerJoint inspection, periodic audits, survelliance audits, NCR records
- CQA LeadMajor-NCR sign-off, portfolio scoring, pattern reviews
- CQA Headcontinous improvement, audit, monitoring, pattern reviews, SoPs
- EHSSafety sign-off on joint post-WIR
- VendorRaises pre-WIR, MAS, MIR, rectifies with evidence, closes NCRs
- CommercialBill workflow triggered on clean WIR closure
- Design (closing the loop)Pattern signals flow back to design choices
- 01MAS approval
- 02Material arrival at gate — MIR raised against in-house supplied or vendor-supplied material
- 03Joint MIR inspection (CM + CQA) against spec / FTP (field test plan) — pass or fail with reasoning
- 04Work execution with continuous CM-owned QC
- 05Pre-WIR raised by contractors before starting controlled activity (e.g. slab pour)
- 06Pre-WIR sign-off by CM (readiness, drawing version, spec citation confirmed)
- 07During-WIR spot checks by CM and CQA at planned hold-points
- 08Post-WIR raised on completion; joint sign-off by CM, CQA, EHS with photos
- 09Clean closure auto-triggers bill workflow in M21; failure raises an NCR
- 10NCR rectification by vendor with photo/test evidence, then CQA verification and closure
- 11Pattern recognition — repeat defects across vendor, project, package, employee — flags surface automatically
- 12Snag
MAS/MIR, WIR, MSS on paper or WhatsApp; sits in CQA queue till they are on site; bill blocked; photos lost. NCRs raised and closed in isolation; CQA scores computed manually and late; same vendor causes the same issue across three projects and nobody connects the dots.
Every MAS/MIR, WIR, MSS digital with photo, location, timestamp, drawing reference. Joint sign-off in hours not days. Bill auto-triggered on clean closure. Failures auto-feed the NCR register; CQA scores auto-computed; repeat-defect and vendor-quality patterns surface as alerts, not as discoveries during manual report review.
BA20 Eden D L12 — KCL raises pre-WIR for slab pour 14 May 9:38 AM. CM signs off at 9:51 AM. Concrete arrives 11:30 AM. During-WIR spot check at 12:05 PM. Post-WIR with 12 photos at 4:42 PM; joint sign-off by CM, CQA, EHS at 5:18 PM. Bill workflow auto-triggered. Meanwhile at Palava T4 — CQA audit raises NCR on flooring level T2 at 9:22 AM; pattern recognition identifies the third NCR this quarter for vendor Sterling, all flooring, two different sites. Sterling auto-flagged in Vendor 360; CPT alerted; Worli tender auto-excludes Sterling. 342 WIRs portfolio-wide, 4.2h average closure; CQA portfolio score 82.4; 3 vendors flagged repeat NCR.
- ·MIR record per material handover
- ·Pre-WIR / during-WIR / post-WIR record with photos
- ·Inspection checklist per activity type
- ·Joint sign-off log (CM · CQA · EHS)
- ·NCR / SOR register with status, severity, closure evidence
- ·Repeat-defect pattern report per vendor and per package
- ·Bill trigger record on clean WIR closure
Inspections informal — WIR on paper, sits with CQA till they are on site, vendor billing waits, photos lost on WhatsApp. NCRs raised and closed in isolation; patterns across projects and vendors not connected; CQA score computed manually and late. Same root cause re-encountered every project; vendors flagged only when an incident is already systemic.
No external system integrations — module operates on internal records.